Marina del Rey Real Estate – MDR Condos – The Willingham Team

September 8, 2011

in Featured,Local News

IMG00190 20101007 0701 e1311882657200 300x242 Marina del Rey Real Estate   MDR Condos   The Willingham TeamPlanned Projects Waterline Projects in Marina Del Rey

  • Phase II Will install approx. 9,500 LF of 18-inch dia. water main along Admiralty Way between Via Marina and Fiji Way. It’s estimated cost is $6,500,000.
  • Schedule: start in Fall of 2010, duration of 12 months
  • Phase III Will install approx. 9,800 LF of 18-inch diameter water main along Via Marina and Fiji Way. It’s estimated cost is $7,000,000.  Schedule: start in summer of 2012, duration of 12 months

Roadway Projects

Admiralty Way Intersections Improvement

  • Intersection Improvements
  • Median Reconfiguration
  • Signing and Striping
  • Traffic Signal Upgrade
  • Street Light Relocation
  • Median Landscape Replacement

Estimated Total Project Cost & Construction Schedule:

  •  Estimated Total Project Cost: $1,950,000
  •  Tentative Construction Schedule: Fall of 2011
  •  Approximate Construction Duration: 6 Months

Admiralty Way Settlement Repair

  •  Roadway Stabilization
  •  Reconstruct the roadway and prevent further settlement of the road and sidewalk
  • Median Reconstruction
  • New Curb and Gutter
  • Install Curb Ramps
  • Replace Existing Chain-link fence
  • Some work on the basin slope

Estimated Total Project Cost & Construction Schedule:

  •  Estimated Total Project Cost: $2,700,000
  •  Tentative Construction Schedule: Winter of 2012, pending completion of the Admiralty Way
  • Waterline Phase 2 project.
  • Approximate Construction Duration: 5-7 Months

 

Admiralty Way at Via Marina

Design Alternatives:

  • There are currently two proposed alternatives for the improvements at this intersection.
  • Triple Left-Turn
  • Continuous Loop
  •  The scope of work will be finalized after the public review of the environmental document which is currently being drafted.

Triple-Left Turn Concept:

  • Triple left-turn from Admiralty Way to Via Marina
  • Double Left-Turn Lanes from Via Marina to Admiralty Way
  • Estimated Total Project Cost & Construction Schedule:
    1. Estimated Total Project Cost: $3,220,000
    2. Tentative Construction Schedule: Fall of 2012
    3. Approximate Construction Duration: 6-9 Months

Purpose:

  • To improve Level Of Service (LOS) and provide congestion relief at the intersection of Admiralty Way at Via Marina.
  • To implement the road improvement required in the Marina Del Rey Local Coastal Admiralty Way at Via Marina Plan (LCP)

Continuous LoopConcept:

  • Reconfigure the existing “T” intersection to create continuous loop around MDR.
  • Replace the existing park and monument at the intersection with two new parks
  • Estimated Total Project Cost & Construction Schedule:
    1.  Estimated Total Project Cost: $6,340,000
    2. Tentative Construction Schedule: Fall of 2012
    3. Approximate Construction Duration: 9-12 Months

Purpose:

  • To improve Level Of Service (LOS) and provide congestion relief at the intersection of Admiralty Way at Via Marina.
  • To implement the road improvements required in the LCP.
  • Improve pedestrian safety
  • Create attractive “Gateway” to MDR

 

 

More to Come!

Incoming search terms:

  • marina del rey california
  • marina del rey road construction
  • pacific avenue marina del rey work city
  • playa del rey real estate
  • road work pacific avenue marina del rey
  • vuta marina fiji

Leave A Reply With Facebook

Marina del Rey Home Search Marina del Rey Home Values

Post by Kirstin Willingham

Kirstin has written 88 articles.



Leave A Reply With Facebook

Leave a Comment

Previous post:

Next post: