Hello ~ 你好 ~ Bonjour ~ שלום ~ नमस्ते ~ Ciao ~ こんにちは ~ Olá ~ Привет ~ Hej ~ Merhaba ~ مدد

Planned Projects Waterline Projects in Marina Del Rey

  • Phase II Will install approx. 9,500 LF of 18-inch dia. water main along Admiralty Way between Via Marina and Fiji Way. It’s estimated cost is $6,500,000.
  • Schedule: start in Fall of 2010, duration of 12 months
  • Phase III Will install approx. 9,800 LF of 18-inch diameter water main along Via Marina and Fiji Way. It’s estimated cost is $7,000,000.  Schedule: start in summer of 2012, duration of 12 months

Roadway Projects

Admiralty Way Intersections Improvement

  • Intersection Improvements
  • Median Reconfiguration
  • Signing and Striping
  • Traffic Signal Upgrade
  • Street Light Relocation
  • Median Landscape Replacement

Estimated Total Project Cost & Construction Schedule:

  •  Estimated Total Project Cost: $1,950,000
  •  Tentative Construction Schedule: Fall of 2011
  •  Approximate Construction Duration: 6 Months

Admiralty Way Settlement Repair

  •  Roadway Stabilization
  •  Reconstruct the roadway and prevent further settlement of the road and sidewalk
  • Median Reconstruction
  • New Curb and Gutter
  • Install Curb Ramps
  • Replace Existing Chain-link fence
  • Some work on the basin slope

Estimated Total Project Cost & Construction Schedule:

  •  Estimated Total Project Cost: $2,700,000
  •  Tentative Construction Schedule: Winter of 2012, pending completion of the Admiralty Way
  • Waterline Phase 2 project.
  • Approximate Construction Duration: 5-7 Months

 

Admiralty Way at Via Marina

Design Alternatives:

  • There are currently two proposed alternatives for the improvements at this intersection.
  • Triple Left-Turn
  • Continuous Loop
  •  The scope of work will be finalized after the public review of the environmental document which is currently being drafted.

Triple-Left Turn Concept:

  • Triple left-turn from Admiralty Way to Via Marina
  • Double Left-Turn Lanes from Via Marina to Admiralty Way
  • Estimated Total Project Cost & Construction Schedule:
    1. Estimated Total Project Cost: $3,220,000
    2. Tentative Construction Schedule: Fall of 2012
    3. Approximate Construction Duration: 6-9 Months

Purpose:

  • To improve Level Of Service (LOS) and provide congestion relief at the intersection of Admiralty Way at Via Marina.
  • To implement the road improvement required in the Marina Del Rey Local Coastal Admiralty Way at Via Marina Plan (LCP)

Continuous LoopConcept:

  • Reconfigure the existing “T” intersection to create continuous loop around MDR.
  • Replace the existing park and monument at the intersection with two new parks
  • Estimated Total Project Cost & Construction Schedule:
    1.  Estimated Total Project Cost: $6,340,000
    2. Tentative Construction Schedule: Fall of 2012
    3. Approximate Construction Duration: 9-12 Months

Purpose:

  • To improve Level Of Service (LOS) and provide congestion relief at the intersection of Admiralty Way at Via Marina.
  • To implement the road improvements required in the LCP.
  • Improve pedestrian safety
  • Create attractive “Gateway” to MDR

 

More to Come!


Invictus and Lady Lola

Similar Posts:

Leave a Comment