Planned Projects Waterline Projects in Marina Del Rey
- Phase II Will install approx. 9,500 LF of 18-inch dia. water main along Admiralty Way between Via Marina and Fiji Way. It’s estimated cost is $6,500,000.
- Schedule: start in Fall of 2010, duration of 12 months
- Phase III Will install approx. 9,800 LF of 18-inch diameter water main along Via Marina and Fiji Way. It’s estimated cost is $7,000,000. Schedule: start in summer of 2012, duration of 12 months
Roadway Projects
Admiralty Way Intersections Improvement
- Intersection Improvements
- Median Reconfiguration
- Signing and Striping
- Traffic Signal Upgrade
- Street Light Relocation
- Median Landscape Replacement
Estimated Total Project Cost & Construction Schedule:
- Estimated Total Project Cost: $1,950,000
- Tentative Construction Schedule: Fall of 2011
- Approximate Construction Duration: 6 Months
Admiralty Way Settlement Repair
- Roadway Stabilization
- Reconstruct the roadway and prevent further settlement of the road and sidewalk
- Median Reconstruction
- New Curb and Gutter
- Install Curb Ramps
- Replace Existing Chain-link fence
- Some work on the basin slope
Estimated Total Project Cost & Construction Schedule:
- Estimated Total Project Cost: $2,700,000
- Tentative Construction Schedule: Winter of 2012, pending completion of the Admiralty Way
- Waterline Phase 2 project.
- Approximate Construction Duration: 5-7 Months
Admiralty Way at Via Marina
Design Alternatives:
- There are currently two proposed alternatives for the improvements at this intersection.
- Triple Left-Turn
- Continuous Loop
- The scope of work will be finalized after the public review of the environmental document which is currently being drafted.
Triple-Left Turn Concept:
- Triple left-turn from Admiralty Way to Via Marina
- Double Left-Turn Lanes from Via Marina to Admiralty Way
- Estimated Total Project Cost & Construction Schedule:
- Estimated Total Project Cost: $3,220,000
- Tentative Construction Schedule: Fall of 2012
- Approximate Construction Duration: 6-9 Months
Purpose:
- To improve Level Of Service (LOS) and provide congestion relief at the intersection of Admiralty Way at Via Marina.
- To implement the road improvement required in the Marina Del Rey Local Coastal Admiralty Way at Via Marina Plan (LCP)
Continuous LoopConcept:
- Reconfigure the existing “T” intersection to create continuous loop around MDR.
- Replace the existing park and monument at the intersection with two new parks
- Estimated Total Project Cost & Construction Schedule:
- Estimated Total Project Cost: $6,340,000
- Tentative Construction Schedule: Fall of 2012
- Approximate Construction Duration: 9-12 Months
Purpose:
- To improve Level Of Service (LOS) and provide congestion relief at the intersection of Admiralty Way at Via Marina.
- To implement the road improvements required in the LCP.
- Improve pedestrian safety
- Create attractive “Gateway” to MDR
More to Come!
Incoming search terms:
- marina del rey california
- marina del rey road construction
- pacific avenue marina del rey work city
- playa del rey real estate
- road work pacific avenue marina del rey
- vuta marina fiji







310-508-8082










Leave A Reply With Facebook